Cornwalls
  • About Us
  • Legal Expertise
  • Industry Focus
  • Our People
  • Working Here
  • Sharing Knowledge
  • Our Community
  • International Reach
Back
     
     

    Field of dreams ... or nightmares

    Posted on: 15 Sep, 2010 |  Contacts: Peter Macnish, Jennifer Holdstock
     

     

    Peter Macnish and Jennifer Holdstock visit North West Southside College and Bonga Binga Small Good School to find out what can go right, and wrong, when schools renovate or upgrade their facilities. The focus is on two differing construction experiences that highlight the importance of good planning, thoughtful contract drafting, diligent project management, input from competent consultants, and the need to be aware of and understand legislation relating to payment claims on construction projects.

    North West Southside College

    The board of North West Southside College is at last in a position to fund a long-awaited renovation and upgrade of its school gymnasium. A member of the building subcommittee with some construction experience arranges for the school's lawyers and an experienced construction project manager to meet with the subcommittee for preliminary discussions - both are happy to do that without charge in the hope that they'll later become part of the consultant team on the project.

     

    Following the meeting, the subcommittee resolves to engage design and other consultants to prepare the design and obtain the necessary planning approval. Once those tasks are completed, it will engage the project manager and lawyer to prepare the tender request and construction contract. These two consultants will provide assistance dealing with tender queries and negotiations with the chosen builder. The project manager will then manage the construction phase, reporting back to the business manager, who in turn will report to the building subcommittee.

     

    Eventually a builder is chosen and a contract entered into for a lump sum price with construction to commence and be completed in six weeks over the Christmas vacation period - the project manager and builder have specifically dealt with issues regarding the procurement of labour, supplies and subcontractors during the vacation period in pre-contract negotiations.

     

    The project begins on time and progresses smoothly. The project manager meets weekly with the builder and the school's business manager and is on site as needed, usually for a couple of hours on two or three days each week. The project manager manages the payment claims and payments, ensuring that claims are promptly passed to the school's quantity surveyor for approval and to the business manager for payment.

     

    Early in the construction period there are several days of heavy rain which delay the project. The builder applies for an extension of time to complete, in accordance with the contract, and the project manager recommends to the business manager that the extension be granted. At the same time the builder and project manager agree on a revised program to bring the project to completion before the commencement of the new school year without additional cost to the school.

     

    While demolishing internal walls, the builder finds asbestos sheeting in poor condition covered up in an earlier renovation. The contract has set out the steps to be taken should such a contingency arise and allows the builder to claim for the extra expense - $15,000 - involved in dealing with the asbestos as if this had been a variation requested by the school. A claim is made and paid. Fortunately, in the early, pre-tender stages, the school's consultants had recommended that the budget include a $50,000 contingency for just such unexpected events.

     

    On day one of the new school year the parents, teachers and students are presented with the rejuvenated gymnasium ready for use. Any defects, should any become apparent, will be dealt with in the six month defect period under the guidance of the project manager. The school board, subcommittee and business manager have delivered the project on time and on budget with minimal stress and worry, having engaged the appropriate design, project management, legal and other consultants to assist.

    Bonga Binga Small Good School

    Bonga Binga Small Good School has been expanding rapidly. It's a new school with a competent and experienced board, but without any directors who have experience in overseeing the running of a primary school or in construction projects. The board determines that a new classroom block will be needed in eight months for the start of the next school year. Funding has been a problem but is now in place. Time is running out.

     

    One of the directors is a passing acquaintance of Bob, the director of Glorious Constructions Pty Ltd, who says that his company can build the project for the money and in the time. Bob's advice to the directors is not to worry too much about the contract terms as they can work those out as they go along. He presents the board with a contract he 'always uses.' It's a standard contract for building work, but drawn heavily in favour of the builder. It later transpires that the builder's lawyers have amended the standard contract in a way that further shifts risks from the builder to the school.

     

    The contract is for a lump sum price; however, the circumstances in which the price can change are almost unlimited. The contract requires the project to be built by the first day of term, but the circumstances in which the builder will be excused for being late are also almost unlimited. In any case, there are no negative consequences for the builder if the project runs overtime.

     

    The board overrides the business manager's suggestion that lawyers be engaged to check the contract and advise generally, as well as his suggestion that a project manager be engaged on a sessional basis to help with day-to-day project management. The board is of the view that the cost is not warranted.

     

    From the start there are problems. The bank is not happy with the contract and amendments need to be made. There are also problems with the building permit and small changes to the plans are required. Bob immediately puts in a claim for a price increase which he is entitled to under the contract. The price increase is reflected in the first payment claim which arrives before the first sod has been turned. The claim is made under Victoria's Building and Construction Industry Security of Payment Act 2002. The board objects and directs the business manager not to pay the extra amount and to tell the builder that the building just has to be finished on time. In due course, Bob is paid the lesser amount and says nothing.

     

    Start up is delayed with very little work done before 24 December. Bob announces that he will be taking two weeks Christmas leave and puts in a claim for extra time due to the bank and permit delays, even though the contract and building permit were his responsibility. The contract is ambiguous as to Bob's claim for time; however, there is an argument that he is entitled to the extra time.

     

    The board is furious and directs the business manager to ignore the claim, but tells Bob to finish on time 'or else.' The business manager is struggling in his dealings with the builder - each time he raises an objection to Bob's claims, the builder gets the contract out and points to yet another clause unfavourable to the school.

     

    Two weeks into the new school year the new classroom block is not yet finished. Fortunately, the weather is fine, allowing for plenty of outdoor sporting events and nature study classes, although the school has had to hire space in the local community centre at its own considerable and unbudgeted expense.

     

    Bob gives the school notice that the project is complete, despite the site being strewn with building debris, mounds of earth and other rubbish. When the business manager objects, Bob tells him to check the contract, which he does, and finds that the builder has the final say on what constitutes the finished job and that there is no obligation on the builder to leave the site clean and tidy.

     

    The final payment claim arrives, as with all the others, served pursuant to the Building and Construction Industry Security of Payment Act 2002. It's enormous, and includes the numerous earlier claims for increases to the price and also the numerous claims for extra time to complete, which the school has ignored.

     

    The board directs the business manager not to pay and to instruct lawyers versed in construction law. At a meeting with the board, the lawyers deliver their advice. It's all bad news. The contract puts the school in a very difficult position since virtually all the claims for extra time and money are permitted under the contract, which specifically precludes the school from claiming for its costs such as the cost of the hire of the community centre.

     

    Salt is rubbed into the wounds when the lawyers advise that the school's failure to object to amounts claimed under the Building and Construction Industry Security of Payment Act 2002 within 10 business days of the claim has resulted in the board becoming immediately liable to pay the full amount of all money claimed regardless of merit.

     

    In short, the school must pay up now and sue to recover any resulting overpayment. The advice regarding recovery of any overpayment is that it will take at least 10 months, it will be very expensive and it might not succeed because of the contract's heavy bias in favour of the builder.

     

    With a limited budget and cash flow, the school is forced to take out an expensive short-term loan, guaranteed personally by the directors, and to go to the parents with an apology and a request to double their fundraising efforts.

     

    Teachers and students, meanwhile, are grumbling about the mess and poor workmanship. There's no six-month defect period and the builder is arguing about every defect pointed out by the business manager.

     

    Without the good and timely assistance of experienced consultants, the school has been ill equipped to deliver the project.

     

    The business manager, who is very popular with parents, is actively looking for a position with another school.

    Lessons learned

    With all the school construction work being undertaken around the country at the moment, it's timely to think about what can go wrong.

     

    The importance of a well-documented contract, solid project management and the appropriate use of consultants cannot be over-emphasised. The experience at Bonga Binga Small Good School also highlights the pitfalls of disputed payment claims and of failing to understand the significance of the security of payment legislation. Failure to deal properly with disputed payment claims can result in the claim becoming payable immediately, without regard to the merits of the claim.

     

    As a checklist, ensure that:

    • proper scoping and design work is done at the outset - not on the run;
    • formal contract documentation is in place, delivered with the request for tender - your legal team is behind the eight ball if the price or contract terms are all but agreed before it's consulted;
    • payment claims are dealt with expeditiously - seek immediate advice if you think that a dispute is looming;
    • pricing and timing mechanisms are clearly set out in the contract and understood; and
    • variations are properly documented and agreed at the time that they arise.

    Legal and project management advice at the outset will always be cost effective, when compared with the cost and inconvenience of intractable disputes arising out of poor documentation and poor project management. Protect your school's interests, by utilising your school's consultant team in a timely way.

     

    North West Southside College and Bonga Binga Small Good School are entirely fictitious, as are the case study details described above. Any similarity with any actual school is unintended.

    (Authored by Peter Macnish and Jennifer Holdstock)


    RELATED INFORMATION

    LEGAL EXPERTISE

    • Commercial Litigation
     

    INDUSTRY FOCUS

    • Construction
     

    SUBSCRIBE

    Register for our Legal Expertise and Industry Focus updates.Register


    CornwallStodart

    Contact Us | Disclaimer | Privacy | Site Map 
    Client Feedback

    Level 10, 114 William Street, Melbourne VIC 3000, Australia | Phone +61 3 9608 2000 | Fax +61 3 9608 2222
    Copyright © 2010 Cornwall Stodart Enhancing Success ®. All rights reserved.